10 Ways Data Centre Handovers Go Wrong

…and how to prevent them. June 2026 · GRANSKA Team

A data centre fit-out costs millions of euros, and launch day should be flawless. In our experience, most handovers include at least one "we didn't think about that" moment. Some include several. Here are ten ways things commonly go wrong — and the documentation discipline that prevents each one.

1. Missing or incomplete Inspection & Test Plans (ITPs)

Commissioning teams arrive on site and key systems have no ITPs — or the ITPs are missing acceptance criteria, witness authority, or test procedures. Testing ends up ad-hoc, defects go undocumented, and the final sign-off is weak because the rigour was never there.

2. Electrical defects — non-compliance with SFS 6000

Earth fault loop impedance out of tolerance, protective devices that don't coordinate, cables routed with mechanical damage risk, labelling missing. Found late, these halt commissioning for weeks of remediation and re-certification.

3. Cooling systems that don't perform to specification

Data halls power up and outlet temperatures run high, consumption exceeds design, racks sit in thermal imbalance — because performance was never verified at part-load and full-load conditions before handover, and containment details were never checked against design.

4. Undocumented design changes

Field teams deviate from approved design — a valve added, a circuit re-routed — without telling the design engineer or recording the change. The as-built documentation then doesn't match the installed reality, and maintenance teams inherit drawings that are quietly wrong.

5. Control systems configured but never truly tested

"It compiles and doesn't crash" is accepted as commissioning. Sensor calibration is unverified, alarm logic untested end-to-end, integration incomplete. The facility then operates without trustworthy environmental visibility.

6. O&M manuals that don't match the building

Manuals arrive incomplete, outdated, or describing equipment that was value-engineered out months ago. The operations team is flying blind, and the first incident becomes chaos because the procedures are wrong.

7. Power distribution that isn't right-sized

UPS overload alarms in normal operation, phase imbalance across PDUs, transfer switches under-rated for peak transients — discovered after handover, when the fix requires downtime.

8. Fire and life safety treated as an afterthought

Suppression uncommissioned, emergency lighting untested, alarm chains never proven end-to-end. Beyond the catastrophic risk, this is regulatory non-compliance — and insurers can decline claims where commissioning evidence is missing.

9. No-load commissioning

Systems are commissioned at partial load "to save time", with full-load operation deferred to live service. Issues then surface in production, where diagnosis is slow and reputations are on the line.

10. Weak handover sign-off

"The system is ready" — with no definition of ready. Open defects acknowledged but never formally dispositioned. The owner accepts responsibility for things they don't know about, and warranty disputes follow.


The common thread

Every one of these failures leaves a documentation fingerprint long before it becomes a site problem. A missing ITP, an uncertified test, an as-built that doesn't match reality — these are all catchable in a structured documentation review, weeks before the main contractor or owner finds them.

That is exactly what we do: independent, standards-traced review of ITPs, test packs, and handover documentation, with a clear Pass/Fail recommendation. See how a review works, or tell us what you're preparing.